AmeriPro Environmental ServicesFLOOD RESPONSE / DESIGN DEVELOPMENT
REV B / CONCEPT STUDY / NOVEMBER 2026

Built around
the mission.

Candidate arrangements and numerical envelopes for design review. All dimensions, masses and loads below are proposed allocations, not measured or vendor-certified specifications.

MFP-500 / DIESEL-DRIVEN CANDIDATE20 ft equipment deck · 9,500 lb loaded mass ceiling
DRYFORCE / DESICCANT CANDIDATE24 ft equipment body · 12,000 lb loaded mass ceiling
DESIGN DECISIONKeep pumping and drying independently deployable
INTERACTIVE / GENERAL ARRANGEMENT

Explore the trailer zones.

Click a component or select it below. Drawings show nominal body dimensions, not overall road length. Tow connection and running gear are schematic.

Component selection

ARRANGEMENT DECISIONS

Reserved service strip: 30 in nominal. Actual clearances, door swings and egress require a dimensioned vendor layout. Longitudinal positioning remains subject to axle / hitch reaction analysis.

Process interfaces
INTERACTIVE / CHANGE THE ALLOCATIONS

Close the design envelope.

Equipment packages below include their normal service fluids unless the dedicated fuel row says otherwise. Reserve is unallocated mass, not permission to exceed a trailer rating.

Loaded mass budget
PACKAGING CHECK
Allocated loaded mass—
Remaining design reserve—

Certification must separately address trailer GVWR, axle / tire ratings, hitch load, tow-vehicle ratings and actual weighed condition. No towing classification is assigned.

DryForce connected-load study
POWER ARCHITECTURE STUDY
Connected real power—
Real-power planning envelope with reserve—

This is arithmetic load aggregation, not generator selection. Apparent power, power factor, starting current, phase balance, heater staging, ambient derating and duty rating remain unresolved.

The weight allocation for a power package does not establish that a package meeting this electrical envelope will fit. Electrical and mass budgets must be reconciled together.

COORDINATED DEPLOYMENT

Three interfaces to resolve.

WATER

Intake & discharge

Define water condition, screen access, hose length and elevation to an authorized receiving point. The pumping trailer performs no treatment.

AIR

Supply & return

Reserve separate process-air return and dry-air supply connections. Keep regeneration wet-air exhaust and engine exhaust separate from building intakes.

SERVICE

Independent support

Each trailer retains local controls and service access. No shared control link or potable-water connection is required by this concept.

Next design review

Choose the pump duty point and the DryForce ambient / moisture envelope, then replace the allocations with supplier dimensions, curves, mass and electrical data.

Read Rev B notes →

Technical background: Xylem pump-selection guide and Munters desiccant-system overview. These references explain design principles; they do not validate the proposed AmeriPro dimensions or budgets.

Continue to deployment

Explore the proposed site layout, connection schedule and fault-response review for the two-trailer team.

Deployment & controls →