AmeriPro Flood Response Team — Preliminary BOM & Cost Basis

Revision A · November 7, 2026

Planning allowances in USD, to be replaced with comparable supplier quotations once the design envelope is set.

MFP-500 allowance schedule

Functional packageQuantity basisPlaceholder allowance
Trailer platform, enclosure / guarding and service provisions1 concept platform$18,000
Pump, drive and priming package1 functional set; final architecture open$38,000
Suction / discharge hoses, screen and couplings1 mission kit; diameters / lengths TBD$12,000
Controls, instruments and optional telemetry allowance1 package$7,000
Hose storage, containment and accessories1 package$5,000
Integration labor and acceptance testing1 allowance$15,000
MFP-500 subtotal$95,000

DryForce allowance schedule

Functional packageQuantity basisPlaceholder allowance
Trailer platform, enclosure and service provisions1 concept platform$22,000
Dehumidification package1 allowance; module count / technology TBD$50,000
Power provision and electrical distribution1 allowance; architecture / rating TBD$28,000
Ducts, distribution fans and air movers1 mission kit; quantities TBD$15,000
Temperature / humidity / material-moisture instrumentation1 field kit$5,000
Integration labor and acceptance testing1 allowance$25,000
DryForce subtotal$145,000

Combined concept budget

ItemCalculationAllowance
Base pair$95,000 + $145,000$240,000
Concept contingency20% × $240,000$48,000
Illustrative pair capitalBase + contingency$288,000

Contingency covers unresolved design. Taxes, freight, tow vehicles, licensing / registration, financing charges, working capital, spare fleet capacity, special contamination equipment and site-specific work are excluded. Engineering / certification beyond the integration allowances requires separate pricing.

The companion planner starts at $288,000 but accepts a replacement capital figure. Changing it does not change this underlying schedule. Scenario JSON downloads preserve the entered assumptions and units for review.

Illustrative annual operating scenario

Assumption / outputValueBasis
Pair revenue$3,500 / billable dayPlanning value
Variable operating cost$1,600 / billable dayPlanning value for the pair
Contribution per billable day$1,900Revenue less variable cost
Annual billable pair days45Assumed utilization, not a forecast
Annual fixed operating costs$36,000Planning value
Annual gross revenue$157,500$3,500 × 45
Annual operating surplus$49,500$1,900 × 45 − $36,000
Operating break-even19 billable pair days / yearRound up $36,000 ÷ $1,900
Simple capital paybackApproximately 5.82 years$288,000 ÷ $49,500

Operating break-even covers fixed operating costs, not the purchase price. The surplus is before financing, taxes, depreciation and replacement capital. With a nonpositive daily contribution there is no positive-margin break-even; with nonpositive annual surplus there is no simple payback.

For the model, one billable day means a charged day for the pair. Pump-only, drying-only, standby and mobilization pricing require separate scenarios; do not multiply a single trailer's days into pair revenue.

Quote and operating-cost checklist

Obtain matched-duty pump quotes and drying quotes for the intended site conditions. Require written inclusion lists for controls, power, hoses, ducts, freight, commissioning, warranty and service support. Identify exclusions and compare duty points before comparing prices.

Replace the daily-cost allowance with labor hours and burden, fuel / electricity, maintenance reserve, consumables, disposal and subcontractor costs. Allocate mobilization / demobilization and nonbillable setup explicitly. Replace annual fixed costs with storage, insurance, administration and other recurring costs, avoiding double counting against daily costs. Show debt service and working capital separately if financing is pursued.

Proceed to procurement only after the concept validation gates close and management approves a supplier-backed budget.